All construction plans approved by the City of Marysville must include general notes that govern the construction methodologies used by the construction contractor for a particular project. Infrastructure that will be maintained by the City of Marysville must be constructed in compliance with the technical specifications approved by the city engineer. All applicable standard drawings must be referenced within all approved construction plans:
- General Notes - This information must be included on all approved construction plans.
- Supplemental General Design Specifications - Information for the Design Engineer
- Access Management Guidelines - Enforced by the Engineering Department.
- Traffic Impact Study Requirements - May be required by the Engineering Department.
- Active Transportation Map - Outline of walking and bicycle routes in the city.
- Thoroughfare Plan
- Construction in and Around Airports - Board of Building Standards
- Bid Postings
Permits & Applications
The Engineering Department requires the inspection of any work on the city’s public infrastructure including the utilities located in the county. Inspections must be scheduled a minimum of 24 hours in advance.
- Water/Sewer Connection (In City Limits)
- Water/Sewer Connection (Outside City Limits)
- Business Registration Application
- Application for Contractor’s License - The intent of the licensing process is to ensure that contractors meet the minimum qualifications and experience to perform the specified work. A bond supplied by the contractor is required to protect the city from any damages that may arise from said work.
- Flood Hazard Area Development Permit
- Homeowner’s Statement - Only necessary if the homeowner, themselves, are performing the construction work on public infrastructure.
- Right-of-Way Permit
- Sidewalk & Curb Improvement Program Application
- Sidewalk & Curb Improvement Program Guidelines
- Zoning Permits
- Marysville Supplemental Specifications - These specifications must be followed during the engineering design and contractor installation of any project that includes roadway improvements within the city right-of-way.
- Ohio Department of Transportation (ODOT) - These specifications must be followed during the engineering design and contractor installation of any project that includes roadway improvements within the city right-of-way.
- Street Notes - This information must be included on all construction plans that include roadway improvements within the city right-of-way.
Streets Standard Drawings
All applicable drawings must be referenced within all constructions plans that include roadway improvements with the city right-of-way.
Drawing Number | Drawing Name | Last Revision |
---|---|---|
STR | All Street Standard Drawings | 03/24/2023 |
STR-01 | Standard Sidewalk | 1/1/2020 |
STR-02 | Residential Roof Drain | 1/1/2020 |
STR-03 | Shared Use Path | 03/24/2023 |
STR-04 | Pavement and Utility Cut Repair | 4/1/2021 |
STR-05 | Combined Curb and Gutter | 1/1/2020 |
STR-06 | Type 6-18 inch Straight Curb | 1/1/2020 |
STR-07 | Residential Driveway | 1/1/2020 |
STR-08 | Commercial Driveway Flare | 1/1/2020 |
STR-09 | Commercial Driveway Radius | 1/1/2020 |
STR-10 | 29’-0" Street Pavement Section | 6/6/2022 |
STR-11 | 35’-0" Street Pavement Section | 6/6/2022 |
STR-12 | 39’-0" Street Pavement Section | 6/6/2022 |
STR-13 | Street Pavement Sections | 1/1/2020 |
STR-14 | Rigid Pavement Relief Joint | 1/1/2020 |
STR-15 | Backfill within Right-of-Way | 1/1/2020 |
STR-16 | Curb Ramps | 1/1/2020 |
STR-17 | Street Signs | 03/24/2023 |
STR-18 | Traffic Signal Standards | 1/1/2020 |
STR-19 | Right-In / Right-Out | 4/1/2021 |
- Stormwater Drainage Manual - This document outlines the regulations pertaining to stormwater conveyance (storm sewer design, flood routing, etc.) and drainage pond (i.e. retention/detention basins) design. These specifications must be followed during the engineering design and contractor installation of any project that includes public stormwater facilities.
- Flood Plain Management Regulations
- Stormwater Notes - This information must be included on all construction plans that include public storm system improvements within the city right-of-way.
Stormwater Standard Drawings
All applicable drawings must be referenced within all construction plans that include public storm system improvements.
Drawing Number | Drawing Name | Last Revision |
---|---|---|
STS | All Stormwater Standard Drawings | 03/24/2023 |
STS-01 | Catch Basin (< 24" Pipe) | 03/24/2023 |
STS-02 | Catch Basin (≥ 24" Pipe) | 03/24/2023 |
STS-03 | Catch Basin Grate | 3/14/2018 |
STS-04 | Curb and Gutter Inlet | 3/14/2018 |
STS-05 | Curb and Gutter Inlet - Frame & Grate | 3/14/2018 |
STS-06 | Type C Precast Manhole | 3/14/2018 |
STS-07 | Manhole Details | 3/14/2018 |
STS-08 | Manhole Base Channel | 3/14/2018 |
STS-09 | Precast Headwall (< 36" Pipe) | 3/14/2018 |
STS-10 | Precast Endwall (< 60" Pipe) | 3/14/2018 |
STS-11 | Cast-In-Place Headwall (≤ 36" Pipe) | 3/14/2018 |
STS-12 | Cast-In Place Headwall (> 36" Pipe) | 3/14/2018 |
STS-13 | Cast-In-Place Endwall | 3/14/2018 |
STS-14 | Trench Detail | 4/1/2021 |
Sediment & Erosion Control Standard Drawings
All applicable drawings must be referenced within all construction plans that include Sediment & Erosion Control Measures.
Drawing Number | Drawing Name | Last Revision |
---|---|---|
SEC | All SEC Standard Drawings | 12/29/2017 |
SEC-01 | Dandy Bag | 12/29/2017 |
SEC-02 | Beaver Dam | 12/29/2017 |
SEC-03 | Linear Sediment Barrier (Silt Fence) | 12/29/2017 |
- Wastewater Master Plan
- Wastewater Notes - This information must be included on all construction plans that include public sanitary sewer system improvements.
- Wastewater Specifications - These specifications must be followed during the engineering design and contractor installation of any project that includes public sanitary sewer system improvements.
- Capacity Fees - Capacity fees for Water and Wastewater based upon meter sizing. Please contact the Engineering Department at (937) 645-7350 for specific questions regarding utility capacity fees.
Wastewater Standard Drawings
All applicable drawings must be referenced within all construction plans that include public sanitary sewer system improvements.
Drawing Number | Drawing Name | Last Revision |
---|---|---|
SAS | All Wastewater Standard Drawings | 03/24/2023 |
SAS-01 | Typical Trench Inside & Outside Pavement Limits | 03/24/2023 |
SAS-02 | Typical Service Lateral | 03/24/2023 |
SAS-03 | Typical Riser and Cleanout | 03/24/2023 |
SAS-04 | Typical Clay Dam | 03/24/2023 |
SAS-05 | Dual Lateral Extension | 03/24/2023 |
SAS-06 | Manhole Base Channelization | 03/24/2023 |
SAS-07 | Pre-Cast Type A Concrete Manhole | 03/24/2023 |
SAS-08 | Manhole Cover | 03/24/2023 |
SAS-09 | Manhole Steps | 03/24/2023 |
SAS-10 | Drop Manhole | 03/24/2023 |
SAS-11 | Typical Watertight Manhole Casting | 03/24/2023 |
SAS-12 | Chimney Seal and Wrapidseal Detail | 03/24/2023 |
SAS-13 | Manhole Marking | 03/24/2023 |
SAS-14 | Typical Automatic Air Release Valve | 03/24/2023 |
SAS-15 | Typical Concrete Encasement | 03/24/2023 |
SAS-16 | Utility Crossing Replacement Detail | 03/24/2023 |
SAS-17 | Jack & Bore Detail | 03/24/2023 |
SAS-18 | Inspection Manhole | 03/24/2023 |
SAS-19 | Mandrel Detail | 03/24/2023 |
SAS-20 | Open Cut Point Repair & Wye Abandonment | 03/24/2023 |
- Water Notes - This information must be included on all construction plans that include public water system improvements.
- Water Specifications - These specifications must be followed during the engineering design and contractor installation of any project that includes public water system improvements.
- Capacity Fees - Capacity fees for Water and Wastewater based upon meter sizing. Please contact the Engineering Department at (937) 645-7350 for specific questions regarding utility capacity fees.
Water Standard Drawings
All applicable drawings must be referenced within all construction plans that include public water system improvements.
Drawing Number | Drawing Name | Last Revision |
---|---|---|
WTR | All Water Standard Drawings | 03/24/2023 |
WTR-01 | Fire Hydrant | 03/24/2023 |
WTR-02 | Corner Lot Service Connection | 03/24/2023 |
WTR-03 | Restrained Joints | 03/24/2023 |
WTR-04 | Jack & Bore | 03/24/2023 |
WTR-05 | Heavy Duty Valve Box | 03/24/2023 |
WTR-06 | Waterline Lowering | 03/24/2023 |
WTR-07 | Water meters and Vaults | 03/24/2023 |
WTR-08 | Tracer Wire | 03/24/2023 |
WTR-09 | Trench Detail | 03/24/2023 |